The need
The family-run hotel had been renewed piecemeal over the years, leaving rooms that looked different from one another and dated. Bathrooms, too few sockets, poor lighting and corridor noise were the most frequent complaints in guest reviews. The budget was limited and the season opening could not be delayed.
Design approach
We developed a single standard room design with two variations for all rooms. Standardising repeated details reduced both cost and build time. In the bathrooms we removed the baths and created glass-screened showers. Reading lights and USB sockets were added at the bedside, with a luggage niche at the entrance. The palette was kept to sandy tones and olive green, and the lobby became a warm welcome area with local stone and timber.
Delivery
Work progressed floor by floor from November to April, never moving on until a floor was complete. Room furniture was made to measure and delivered in one go. Fixed weekly site days and photo reports kept the owner informed at every stage.
Result
The hotel was handed over ready for the season at the end of April, as planned. The owner told us that complaints about bathrooms and noise dropped noticeably in guest reviews in the first season after the refurbishment.